How Long Does a Kitchen Renovation Take? (GTA Timeline)
A GTA kitchen typically takes 6 to 10 weeks on site, and cabinet lead times of 6 to 10 weeks before install usually set the real schedule. The countertop template-to-install gap is the classic mid-project pause.
HomeCopilot Editorial
A kitchen has more moving parts than any other room — cabinets, counters, appliances, plumbing, electrical, and finishes, several of which depend on each other. Most GTA kitchens take six to ten weeks of on-site work, but the real clock often starts weeks earlier, when the cabinets are ordered.
Timeline · 7 weeks
A typical on-site sequence — about seven weeks; note the countertop template-to-install gap in the middle.
What sets the real schedule
- Cabinet lead time — semi-custom and custom cabinets often take 6 to 10 weeks to arrive, and nothing else can finish until they are in.
- The countertop gap — counters are templated only after cabinets are installed, then fabricated off-site, which is the classic one-to-two-week pause in the middle of the job.
- Moving the layout — relocating plumbing, gas, or a wall adds rough-in and inspection time.
- Appliance and fixture lead times — a back-ordered range or panel-ready fridge can hold up the final week.
FAQ
Why is there a gap after the cabinets go in?
Countertops can only be templated once the cabinets are installed and level, then the slab is cut and fabricated off-site. That template-to-install window is typically one to two weeks, and it is normal — not a stall.
Can I use my kitchen during the renovation?
Usually not for most of it. Plan a temporary kitchen — a fridge, microwave, and kettle in another room — for roughly the full on-site period, since the sink and range are out for much of the job.