How Long Does a Kitchen Renovation Take? (GTA Timeline)

A GTA kitchen typically takes 6 to 10 weeks on site, and cabinet lead times of 6 to 10 weeks before install usually set the real schedule. The countertop template-to-install gap is the classic mid-project pause.

HomeCopilot Editorial

A kitchen has more moving parts than any other room — cabinets, counters, appliances, plumbing, electrical, and finishes, several of which depend on each other. Most GTA kitchens take six to ten weeks of on-site work, but the real clock often starts weeks earlier, when the cabinets are ordered.

Timeline · 7 weeks

Project phase timelineProject phases: Demolition & prep about 1 week; Plumbing, electrical & framing about 1 week; Drywall, paint & flooring about 1 week; Cabinet installation about 1 week; Countertop template & fabrication about 2 weeks; Backsplash, appliances & finish about 1 week.Demolition & prep1wPlumbing, electrical & framing1wDrywall, paint & flooring1wCabinet installation1wCountertop template & fabrication2wBacksplash, appliances & finish1w

A typical on-site sequence — about seven weeks; note the countertop template-to-install gap in the middle.

What sets the real schedule

  • Cabinet lead time — semi-custom and custom cabinets often take 6 to 10 weeks to arrive, and nothing else can finish until they are in.
  • The countertop gap — counters are templated only after cabinets are installed, then fabricated off-site, which is the classic one-to-two-week pause in the middle of the job.
  • Moving the layout — relocating plumbing, gas, or a wall adds rough-in and inspection time.
  • Appliance and fixture lead times — a back-ordered range or panel-ready fridge can hold up the final week.

FAQ

Why is there a gap after the cabinets go in?

Countertops can only be templated once the cabinets are installed and level, then the slab is cut and fabricated off-site. That template-to-install window is typically one to two weeks, and it is normal — not a stall.

Can I use my kitchen during the renovation?

Usually not for most of it. Plan a temporary kitchen — a fridge, microwave, and kettle in another room — for roughly the full on-site period, since the sink and range are out for much of the job.